SHARE THIS

Enon, Ohio 

The progress continues at Greenon Local School District’s new K-12 School.  The 200,000 sf Facilities Project is marching forward with the majority of work now being done under roof.

Structural steel and roof membranes are complete for the entire facility, and roofers are working on the core of the building beginning with the kitchen and mechanical room spaces.  

In the Elementary Wing: 

  • Brickwork is near completion
  • 1st floor drywall is almost complete
  • 2nd floor drywall is ongoing 
  • Lighting control wiring is being finished up
  • 2nd floor ductwork insulation is ongoing 
  • Painters began block fill this week 

In the High School Wing:

  • Courtyard brickwork is near completion
  • Gym roof decking is being installed
  • 2nd floor interior wall framing is ongoing
  • 2nd floor domestic water is complete 
  • 2nd floor ductwork is being hung

Don't miss progress updates for Greenon Local Schools' new K-12 School.  Follow Summit Construction on Instagram and LinkedIn