SHARE THIS

Lancaster, Ohio 

Lancaster’s new junior high schools Thomas Ewing and General Sherman are progressing according to schedule.

Progress update for Lancaster Thomas Ewing:

Interior

  • Flooring in the building is 75% complete
  • Carpet in the administration wing is complete 
  • Concrete polishing and resinous floors are being finished up in the next 2 weeks
  • HVAC testing and balancing are beginning this week
  • Final coats of paint are now being applied in the academic wings    
  • Electricians are finishing up fire alarm devices
  • Communication subcontractors are pulling wire and devicing out rooms
  • Wood doors are being installed

Exterior 

  • All curbs and sidewalks will be finished up this week
  • Paving in the front of the school is complete and the back lot is beginning now
  • Permanent seeding surrounding the building is complete
  • The athletic fields are now being seeded and graded 
  • The athletic track is paved 
  • The athletic storage building construction has begun 

Progress update for Lancaster General Sherman: 

Interior

  • Drywall in the academic areas have begun
  • Plumbing subcontractors are installing water lines in the academic wings - insulators will follow 
  • HVAC subcontractors are finished with ductwork and hydronic piping above the ceiling - They are now working in the mechanical rooms and hooking up air handling units - insulators to follow
  • Fire protection rough-in is about 75% complete
  • Glass window installation has begun
  • Electricians are starting to pull wire 
  • Painting will begin this month 

Exterior

  • Brick work is about 75% complete and brick cleaning has started
  • Curbs and sidewalks have started on the Southside of the site
  • The athletic fields have been graded and permanently seeded


Stay updated with the Lancaster Junior High projects and follow us on LinkedIn and Instagram