Lancaster, Ohio
Lancaster’s new junior high schools Thomas Ewing and General Sherman are progressing according to schedule.
Progress update for Lancaster Thomas Ewing:
Interior
- Flooring in the building is 75% complete
- Carpet in the administration wing is complete
- Concrete polishing and resinous floors are being finished up in the next 2 weeks
- HVAC testing and balancing are beginning this week
- Final coats of paint are now being applied in the academic wings
- Electricians are finishing up fire alarm devices
- Communication subcontractors are pulling wire and devicing out rooms
- Wood doors are being installed
Exterior
- All curbs and sidewalks will be finished up this week
- Paving in the front of the school is complete and the back lot is beginning now
- Permanent seeding surrounding the building is complete
- The athletic fields are now being seeded and graded
- The athletic track is paved
- The athletic storage building construction has begun
Progress update for Lancaster General Sherman:
Interior
- Drywall in the academic areas have begun
- Plumbing subcontractors are installing water lines in the academic wings - insulators will follow
- HVAC subcontractors are finished with ductwork and hydronic piping above the ceiling - They are now working in the mechanical rooms and hooking up air handling units - insulators to follow
- Fire protection rough-in is about 75% complete
- Glass window installation has begun
- Electricians are starting to pull wire
- Painting will begin this month
Exterior
- Brick work is about 75% complete and brick cleaning has started
- Curbs and sidewalks have started on the Southside of the site
- The athletic fields have been graded and permanently seeded
Stay updated with the Lancaster Junior High projects and follow us on LinkedIn and Instagram.