Carroll, Ohio
Bloom-Carroll Local Schools’ new 108,000 SF K-5 Elementary is progressing beautifully. Structural steel is nearly complete, and cold formed metal trusses are beginning to set in place this week on the east end of the building.
On the first floor of the school, all bearing walls are complete. Temporary electric is running and overhead electric is beginning soon. Plumbing chases and above ceiling plumbing is ongoing, and ductwork is being hung. On the second floor, precast planks have been set and the topping slab has been poured.