Akron, Ohio
07/12/23
This spring, Summit Construction was awarded as CMR for the Akron Zoo Facilities & Grounds Building, designed by TC Architects.
The new 8,932 SF single-story building with a partial mezzanine will support the Zoo’s operations through the addition of administrative spaces, meeting rooms, locker room, restrooms, storage, maintenance shop, and parking.
As we approach mid-July, construction is in full swing and moving along on schedule.
Update from the Project Team:
- Foundation walls are complete
- Under slab rough-ins for electrical and plumbing have begun
- Retention pond on schedule for completion this week
- Storm sewer is 80% complete
- Water and sanitary tie-ins are beginning this week