Lancaster, Ohio High School senior, Marcus Smith’s goal of becoming a carpenter was made a reality last week when he signed with Summit Construction Company on SkillsUSA National Trades…
Tallmadge, Ohio Since our last update, the SummaHealth Medical Center has greatly progressed. On the first floor, framing is complete and in wall rough ins are underway. On the second…
Lancaster, Ohio General Sherman Jr. High School is progressing on schedule! All structural steel is complete in the academic areas and the gymnasium Concrete is complete in the academic…
Boston Heights, Ohio Since our last update the Akron Children’s Hospital Health Center is progressing on schedule! Brick on the facade of the building has begun and stone around the…
Lancaster, Ohio It’s an exciting time for Lancaster City School District as the groundbreaking ceremony for their seventh new school took place last week for General Sherman Junior High…
Akron, Ohio Since our last post at Middlebury Commons, the building has greatly progressed inside and out. Here is what’s going on now. Site work structures like the parking…
Cleveland, Ohio A notable step forward has commenced for Urban Community School students, families and those in the surrounding community. Construction for the MetroHealth Center has…
A new 3D rendering video walk through has been released showing what Greenon K-12 School will look like. Summit Construction, and SHP Leading Design gave presentations about the schools…
Tallmadge, Ohio The progress continues at the SummaHealth Tallmadge Medical Center! The 35,000 SF building is located on North Avenue in Tallmadge. See what’s going on inside as we…
Boston Heights, Ohio The Akron Children’s Hospital Health Center is coming to life more and more each day! Framing and electrical are complete on both floors, stairwells are…